The town has received an update from the federal government as it pertains to the former Boblo dock on Front Road South.

CAO John Miceli brought a report to council which stated that he was advised by William Ariss of the Real Property Division of the Central & Arctic Region of Fisheries and Oceans Canada advising the Boblo dock would not be declared surplus at this time. Miceli reported that Ariss advised the town that the department is undertaking “a review of the various wharfs in the Sarnia to Amherstburg corridor” and that upon the completion of that review, “the department will determine whether the wharf is to be repaired, removed, divested or some combination thereof.”

According to Miceli’s report: “Should the Coast Guard determine that the department no longer has an interest in the wharf, then divestiture of the site will be considered. Mr. Ariss has advised that the divestiture process of the wharf requires DFO to offer a site first to other Federal Departments and then to the Province. Mr. Ariss has also advised that it would be difficult at this point (to say) whether the wharf would be transferred to the municipality with monies associated for repairs or if the Department would look to demolish it.”

Cost to repair the pier is estimated at $579,546 with the cost to demolish the pier, including the piles, estimated at $524,807. To demolish the dock, excluding the piles, would carry an estimated cost of $337,488.

The current state of the former Boblo ferry dock is of concern to town council.

The current state of the former Boblo ferry dock is of concern to town council.

“It is important for council to note that the estimates were developed on a Class D level which should not to be considered final and must continue to be refined through the design process. Class D estimates are indicative of a project being considered for budget development and place holder purposes,” Miceli stated in his report.

The CAO added it “would not be unreasonable for one to conclude” that the cost to demolish and replace the dock could be in in excess of $1 million.

Miceli said a decision is not expected before late summer or fall. He added the town is continuing to negotiate with the federal government, saying $337,000 “is the floor. I just can’t tell you what the ceiling is.”

Councillor Rick Fryer believed the dock is a great location for an outlook and for birding opportunities, adding his hope would be for the town can start putting money aside for a project involving the dock so the community can use it.

“I think this is a great opportunity for tourism for the town and for eco-tourism and sports tourism,” he said.

Mayor Aldo DiCarlo questioned whether the town had public access to the dock but Fryer believed access could be looked at as part of the town’s negotiations into the site. Fryer, also chair of the Essex Region Conservation Authority, said ERCA is looking at a possible lookout trail in that area.