Most town roads will require rehabilitation within ten years

 

By Ron Giofu

 

The town’s roads are OK now, but a lot of work looms on the horizon, according to a consultant.

Kyle Edmunds from Dillon Consulting appeared before town council last Tuesday night and presented an updated roads needs report and while that report deemed the roads to be in “fair” condition, it was also determined that 83 per cent of the town’s roads need to be rehabilitated within ten years.

To combat that problem, the town agreed to a plan that would see $1.41 million committed annually over ten years to road work to help combat the deteriorating road system and get some of the more urgent projects completed.

Of the 226.48 kilometres of roads the town controls, about 30.5 per cent need work now while 23.3 per cent need work in the next 1-5 years. About 29 per cent need work within 6-10 years while the remained don’t need work for beyond a decade.

Less than four per cent of Amherstburg’s roads are considered to be in “excellent” condition, as compared to 20.16 per cent in LaSalle and 15.6 per cent in Tecumseh. As for roads in “good” condition, there are 23.38 per cent of roads in Amherstburg in that category as compared to 45.82 per cent in LaSalle and 29.7 per cent in Tecumseh.

Amherstburg has 16.75 per cent of its roads classified in “fairly good” condition with just over 22 per cent of LaSalle’s roads in that category. Tecumseh has 25.5 per cent of its roads classified as “fairly good.”

As for roads in “fair” condition, 27.72 per cent of Amherstburg’s roads fall in that category, as compared to 11.31 per cent in LaSalle and 23.9 per cent in Tecumseh. Amherstburg has nearly 29 per cent of its roads classified as “poor,” as compared to less than one per cent in LaSalle and 5.3 per cent in Tecumseh.

Tecumseh has 181.4 kilometres of road while LaSalle has 187.56 kilometres. They were used by Dillon Consulting as comparators as the firm did roads needs studies in those two municipalities as well over the last few years.

Expect to see more construction signs over the next decade as the town’s road system requires a lot of work. Meloche Road (pictured here, earlier this summer before the road re-opened) is one of the more recent projects the town has undertaken.

Councillor Leo Meloche wondered why the entire focus was on repairing roads that need it now as he said some priority should be put on some of the roads in the 1-5 year category. The poor roads are already poor but the roads in the 1-5 year category will soon join them if not tended to quicker.

“We’re always chasing our tail,” said Meloche.

Councillor Diane Pouget said she didn’t want residents to think it was a “doom and gloom” situation, and added Amherstburg has more roads than Tecumseh and LaSalle.

“That does make a difference,” she said.

Provincial downloading also made a difference, she suggested.

“I think the municipalities started getting into trouble when the province started downloading to us,” she said.

Councillor Rick Fryer pointed out chunks of cement are coming off of Angstrom Dr. and Victoria St. S. is also deteriorating. There are heavily travelled roads like Concession 2 North that are also in disrepair, calling that road “a thoroughfare to LaSalle. It’s one of the worst roads but people use it.”

Traffic counts should not be the only factor in choosing where road projects should be done, Fryer added, as smaller roads need attention too. He said the town should focus on roads instead of “not needed purchases.”

CAO John Miceli called an increase to $1.41 million annually “significant” and said challenges will be ensuring there are enough contractors to do the work and what prices the town gets when projects are put to tender.

“I would suggest the market will indicate where we are going to be,” he said.

Miceli added he would like to see $120,000 in the crack seal program budget to prolong the life of some of the roads.

Councillor Jason Lavigne said the current council has done a lot of road repairs in its first three years.

“I think this council spent more on roads than the last four councils combined,” he said, noting Texas Road and Meloche Road have been upgraded.

Lavigne wanted to know “what will keep politics out of this” when choosing where and when projects get done. Edmunds said all roads have been classified based on a pavement condition index (PCI) and that shows what roads are in the worst condition.

Deputy Mayor Bart DiPasquale also stated that more roads have been repaired this term whereas “in the past, we didn’t do so much.

“Everyone has seen the number of roads that have been fixed in the last little while,” said DiPasquale.

The last complete roads needs study was done by Dillon Consulting in 2003 with a condition assessment update done in 2013.