Demolition resumes at Duffy’s site after delays

 

 

By Ron Giofu

 

Delays have occurred in the demolition of Duffy’s Tavern & Motor Inn but the town’s chief administrative officer states the goal is still to be able to use the site during the Canuck It Up Festival.

Crews could be seen at points last week working at the site as demolition appears to have resumed.

CAO John Miceli said there were issues that caused the demolition to be delayed. One of the issues was a motorcycle crash that injured Jones Group owner Terry Jones.

A Jones Group excavator was seen working at the site of the former Duffy’s Motor Inn Monday morning. Demolition had been delayed at the site but has now resumed.

A Jones Group excavator was seen working at the site of the former Duffy’s Motor Inn Monday morning. Demolition had been delayed at the site but has now resumed.

“We are working with the Jones Group to provide us with a revised schedule as there was a couple of things that did delay the project,” said Miceli. “The first was Terry’s untimely accident and the second was an order that was issued to the Jones Group by the Ministry (of Labour) which has subsequently been lifted.”

Miceli pointed out the Ministry of Labour “has some overarching powers and on this project was seeking written protocols on the demolition process. Unfortunately this  was complicated from a timing perspective with Terry’s untimely accident and has caused some delays.”

The CAO added: “I have been advised by the Jones Group that they will be working diligently to make up time so that we can have access to the site in time for Canuck it Up. I know that the Jones Group knows how important this festival is for the Town and they want to deliver for us.”