Intersection of Pickering Dr. and Sandwich St. S. to close Sept. 1 for watermain installation

The intersection of Sandwich Street and Pickering Drive will be closed to all traffic tomorrow (Friday September 1) to facilitate the installation of a watermain.

The town states the closure is expected to last one day and that detour routes will be posted.

The intersection of Pickering Dr. and Sandwich St. S. will be closed Friday, September 1 for the installation of a watermain.

The intersection of Pickering Dr. and Sandwich St. S. will be closed Friday, September 1 for the installation of a watermain.

Work on the Pickering Drive Watermain Replacement and Road Improvements will be ongoing through October 2017. The town reminds residents that during construction traffic disruptions may occur and some delays may be experienced.

Please slow down, obey all traffic signage, and watch for flag persons in the construction zone.

Town closing Pickering Dr. for watermain replacement and road improvements

Another local road will soon be closed temporarily due to construction.

The town has advised that Pickering Dr. will be closed to through traffic between Dalhousie St. and King St., commencing Aug. 10, to facilitate watermain replacement and road improvements. This closure will be ongoing through October.

Pickering Dr. will get some work this year, including the intersection of Pickering and Sandwich (pictured).

Pickering Dr. will get some work this year, including the intersection of Pickering and Sandwich (pictured).

The town states that local traffic will be maintained and residents will be allowed access to their homes. A detour route will be posted, but delays should be expected.

This capital project will also include a one-day closure of the intersection at Sandwich St. S. and Pickering Dr. next Wednesday (Aug. 16). Detour routes will again be posted.

The town reminds residents that during construction, traffic disruptions may occur and some delays may be experienced. Drivers are asked to please slow down and obey all traffic signage, and watch for flag persons in the construction zone.

The $1.1 million tender was awarded to SLR Contracting Group Inc. in July with manager of engineering Todd Hewitt stating at that meeting that watermain work should take six to eight weeks when it gets started with pavement work coming after that.

Town council approves tender for Pickering Dr. work

 

 

By Ron Giofu

 

Town council has approved a $1.1 million tender for watermain and road improvements to Pickering Dr.

The tender was awarded to SLR Contracting Group Inc. with manager of engineering Todd Hewitt stating watermain work should take six to eight weeks when it gets started. The pavement improvements and intersection work would come after that. The town used Hrycay Consulting Engineers Inc. for its engineering work, Hewitt noted.

Pickering Dr1WEB

In his report to town council, Hewitt pointed out the watermain work will go from King St. to Dalhousie St.

“The watermain on Pickering Dr. has experienced significant breaks in the past. This watermain is critical infrastructure that services a number of large commercial properties that require water to operate. It also currently services four apartment/condominium buildings along Pickering Dr. with another soon to be constructed east of Sandwich St.,” Hewitt stated in his report.

There will also be intersection improvements at Pickering Dr. and Sandwich St. S. with Hewitt noting those improvements will consist of new traffic signals, poles, pedestrian signals, sidewalks and curb upgrades.

Pickering Dr. will get some work this year, including the intersection of Pickering and Sandwich (pictured).

Pickering Dr. will get some work this year, including the intersection of Pickering and Sandwich (pictured).

“Replacing the traffic and pedestrian signals at the intersection of Sandwich Street and Pickering Drive will bring the intersection into compliance with the provincial AODA regulations. Relocating the traffic signal poles and cabinet will better protect them from vehicular damage,” said Hewitt, in his report.

The town had set aside just over $2 million for the project in the 2017 budget. That left $967,301.16 remaining in the total project budget. Hewitt recommended that those savings be used to reduce the issuance of future long term water debt and reduce the 2018 gas tax usage.

“This will be addressed with council during the final reporting of the project,” he stated in his report.